Projects Requiring Designers
Visit the TBR RFPs and RFQs page for a listing of major projects with opportunities for design services.
If you are interested in a project listed below:
- Visit the website of the Office of State Architect to review the updated Designer Selection Process.
- Register with the Office of State Architect.
- Verify registration with the Secretary of State’s office if your business type requires filing.
- Download and save the April 2023
Designer Letter of Interest template
- Complete the document specifically for the project in which you have interest. The response is limited to FOUR pages.
- Save the document as a PDF with the following file convention: Institution-Project Title-Firm Name.pdf
- Send the completed Letter of Interest (in PDF format) to the email link in the list below
Projects Requiring Designers
Campus | Project | MACC | Date Added | Due | |
---|---|---|---|---|---|
Pellissippi SCC |
Magnolia Campus ADA Corrections Update the Magnolia campus to include accessible parking, sidewalks, interior circulation spaces, interior courtyard, and related work for ADA. |
560,000 | 05-20-2025 | 06-10-2025 | |
TCAT - Nashville |
Robertson County Campus Replacement Construct a new campus in Springfield, TN. This project requires designer selection through the RFQ process. Visit the TBR RFP and RFQ website for additional information and instructions. |
31,500,000 | 05-20-2025 | 06-10-2025 | |
Volunteer SCC |
Roof Replacements Replace roof systems on multiple buildings including all related work. Includes work at the Livingston Campus. |
700,000 | 05-20-2025 | 06-10-2025 | |
Pellissippi SCC |
HVAC Equipment Replacement Replace the chiller and cooling tower at the Strawberry Plains Campus. Replace cooling towers at the Hardin Valley Campus. Includes all related work. |
750,000 | 05-21-2025 | 06-10-2025 | |
TSU |
Central Plant Modernization Modernize the main campus central plant, including replacing one boiler, two chillers, one cooling tower, pumps, piping, lighting, electrical, controls, and all related work. Replace the Avon Williams campus chiller, cooling tower, pumps, and related work. The project will be phased to accommodate heating and cooling seasons. |
11,715,000 | 05-21-2025 | 06-12-2025 | |
TSU |
Critical Repairs and Demolition Repair and/or replace plumbing, and mechanical equipment and components in multiple campus buildings. This project may be phased to accommodate ongoing campus operations. |
4,500,000 | 05-21-2025 | 06-12-2025 | |
Northeast SCC |
Hamilton Hall HVAC Replacement Replace the HVAC equipment, piping, ductwork, controls and all associated work in Hamilton Hall. |
1,540,000 | 05-21-2025 | 06-12-2025 | |
TCAT - Memphis |
Aviation Campus Replacement Construct a new Aviation Campus in Memphis, TN. This project requires designer selection through the RFQ process. Visit the TBR RFP and RFQ website for additional information and instructions. |
38,000,000 | 05-20-2025 | 06-16-2025 | |
TCAT - Nashville |
Sumner County Campus Replacement Expand and renovate the campus in Portland, TN. This project requires designer selection through the RFQ process. Visit the TBR RFP and RFQ website for additional information and instructions. |
38,500,000 | 05-20-2025 | 06-16-2025 |